Estimate concrete for a slab or post holes
How many bags for a shed slab or a fence line of post holes? Volume plus the yield printed on your bag.
Tools used in this guide
The job
Concrete comes as dry bags you mix — the question is always 'how many'. Slabs are L×W×D; post holes are cylinders × the hole count. The yield per bag varies by brand, so it is an input, not a guess.
Compute it
Pick slab or post-hole shape, enter the dimensions, and read the yield off your bag (≈9–14 L for typical 20–30 kg bags — it is on the label). Extra allowance covers spillage and a slightly-deep dig.
- Slab: length, width, thickness.
- Post: hole diameter, depth, count.
- 10% extra is the usual buffer for uneven ground.
Worked example
Four post holes at 200 mm diameter × 500 mm deep = 0.063 m³ ≈ 63 L. At 10% extra that's ~70 L; at 12 L per bag, 6 bags. The two-bag spare you nearly bought stays at the store.
Limits
Treats holes as perfect cylinders and slabs as perfect boxes — real ground is neither, so keep the extra allowance honest. Up to 1,000 m³ and 50% extra. Bag yields differ; always check the label.